New life for existing dyke and pump station

Design and construction work on this project meets both federal and provincial dyke design and environmental standards.

Construction was started in the late summer 2012 and was substantially completed by February 2013.

Fifty two construction drawings were completed. These include pump station and dyke upgrading, seepage control, electrical, mechanical, structural, and architectural designs.

The site is located at the south bank of the Fraser River at the north end of No.1 Road.